Start hereRules checked 20 October 2026
Type approval proves that a treatment design works on a test rig. It does not prove that the unit bolted into your engine room, with your pipework, your sampling point and your harbour water, works. That is what the commissioning test is for, and it has been mandatory since 1 June 2022.1 It is not a formality: members of the Global TestNet reported to IMO that about one in five commissioning tests they had carried out was non-compliant, mostly on the largest organisms (50 micrometres and above), although detailed analysis after a failed indicative test often showed the discharge was in fact compliant.8
After commissioning, the system has to keep working for the rest of the ship’s life. In the 2025 port state control campaign the most common deficiency, and the main cause of detentions, was a BWMS that was not operational.10 This lesson follows a BWMS from installation to renewal: the commissioning test, the surveys, the records and maintenance, and what the review approved in 2026 will add.
Free sign-up
Sign up once to open this lesson and every other one in the Academy.
The first 2 lessons of each course are open to all. The rest need a free sign-up, which takes half a minute. We don't issue certificates, and we don't share your details.
In this lesson
- A BWMS from installation to renewal
- In plain words
- In detail
- What the rules say
- Flag and class notes
- Key numbers
- What inspectors find
- Quiz: 6 questions
Try it
A BWMS from installation to renewal
In plain words
A commissioning test is a one-off check, done when a treatment system is first installed or after a major change. The ship takes on local harbour water through the new system, waits the holding time the system needs, then discharges it while an independent tester draws at least a cubic metre of the treated water from a sampling point. The tester counts the living organisms in the two size groups of the D-2 standard, usually with quick “indicative” methods, and checks that the system’s own sensors (flow, pressure, UV intensity, chlorine level and so on) are reading sensibly. If the treated water passes and the sensors are working, the system is accepted.
After that come the regular surveys: annual, intermediate and five-yearly renewal, the same rhythm as other statutory certificates. In between, the crew run and maintain the system, keep the record book, and keep the system’s electronic log. Port state control can check any of this, in any port, and can take samples.
In detail
When a commissioning test is required
Resolution MEPC.325(75) amended regulation E-1 with effect from 1 June 2022. The initial survey, and any additional survey for the installation of a BWMS, “shall confirm that a commissioning test has been conducted to validate the installation” by demonstrating that the system’s “mechanical, physical, chemical and biological processes are working properly”.1 DNV’s reading is that this applies to systems on newbuilds and existing ships whose initial commissioning survey is completed on or after 1 June 2022, even if the system was partly installed earlier, and to additional surveys after a change, replacement or significant repair.7 The resolution also states that the analysis in commissioning testing “should be indicative”.1
How the test is done (BWM.2/Circ.70/Rev.1)
The 2020 Guidance for the commissioning testing of ballast water management systems (BWM.2/Circ.70/Rev.1, 9 December 2020) sets the method:2
- Its purpose is to validate the installation, not the type-approved design.
- Local ambient water is used, however challenging it is for the system.
- After installation, and after all ballast equipment (pumps, piping) is installed and tested:
- at uptake, a sample may be taken to characterise the ambient water (an indicative analysis is enough);
- at the corresponding discharge, after full treatment, a representative sample is taken at the sampling point described in the G2 sampling guidelines, with a total volume of at least 1 m³ (or a smaller volume that has been validated as representative);
- the sample is analysed for both D-2 size classes (50 micrometres and above; 10 to under 50 micrometres) using indicative methods from BWM.2/Circ.42/Rev.2;12
- the system’s self-monitoring parameters are assessed against its design limits and all sensors are confirmed to work.
- The test is successful when the indicative analysis shows that the discharge samples meet D-2 for the size classes analysed.
The Isle of Man registry and DNV both add that sampling and analysis must be independent of the BWMS manufacturer or supplier and acceptable to the flag or its recognised organisation; DNV asks for a DNV-approved service supplier or an organisation accepted by the flag.57 The test report goes to the attending surveyor and, where required, the flag: methods, results with raw data, and the self-monitoring readings.7
Getting it right the first time
Practical experience from testing laboratories points the same way:8
- clean the ballast tank and piping used for the test as well as possible, because organisms and sediment left in the tank or pipes after installation can fail an otherwise good system;
- confirm beforehand that the sampling point exists, is accessible and fits the tester’s equipment;
- ballast the test tank through the BWMS with full treatment and respect the holding time in the type approval certificate before discharging;
- de-ballast long enough for sampling (laboratories typically sample over about an hour of discharge);
- expect the 50 micrometre and larger class to be the critical one.
If the test fails, DNV advises investigating the cause and repeating the test, possibly in another port, and informing the flag Administration and following its advice if a successful repeat is not possible in time.7
Surveys of the BWMS after commissioning
Regulation E-1 sets the same survey cycle as other statutory certificates: an annual survey within three months either side of each anniversary date, an intermediate survey around the second or third anniversary replacing one annual survey, a renewal survey at intervals not exceeding five years, and additional surveys after any change, replacement or significant repair.4 Before the IBWM Certificate is first issued after installation, the BWMS Code asks the Administration to verify the documents on board (type approval certificate, OMSM, BWMP, installation specifications and commissioning procedures) and that the installation conforms.3
Running and maintaining the system
The BWMS Code expects the control and monitoring equipment to record proper functioning or failure, store at least 24 months of data and produce a report for official inspections.3 The OMSM is the maintenance authority: filters, lamps, electrodes, sensors and neutralisation equipment are serviced to the manufacturer’s schedule, by the crew where the manual allows and by the manufacturer’s service engineer where it does not. The BWRB records failures and inoperability under code F.6 The experience-building phase protects a ship from penalties solely for a D-2 exceedance only if the system has been maintained to the manufacturer’s instructions and operated to the BWMP, which is a strong reason to keep maintenance records you can show.11
What the 2026 amendments add
As approved at MEPC 84 for adoption at MEPC 85, the amended regulation E-1 would require renewal and intermediate surveys to confirm that the BWMS is properly installed and achieves D-2; annual surveys to verify required maintenance through the BWRB or an equivalent system and to include annual sampling of residual active substances; and an additional survey when a ship moves from regulation D-4 (prototype) to D-2. A commissioning test would then be needed for that transition unless an identical type-approved system passed an equivalent test in the previous 12 months. After a defect that substantially affects compliance, the owner would have to send a time-bound repair plan to the flag and destination port States.9
What the rules say
- BWM Convention regulation E-1.1.1, as amended by MEPC.325(75) from 1 June 2022, requires the initial survey to confirm that a commissioning test has been conducted to validate the installation of any BWMS.1
- Regulation E-1.1.5, as amended, requires the same confirmation at an additional survey for the installation of a BWMS.1
- MEPC.325(75) operative paragraph 5 resolves that the analysis in commissioning testing “should be indicative”.1
- BWM.2/Circ.70/Rev.1 requires local ambient water to be used and a representative discharge sample of at least 1 m³ to be analysed for both D-2 size classes.2
- BWMS Code paragraph 8.2 requires the type approval certificate, OMSM, BWMP, installation specifications and installation commissioning procedures to be on board.3
- BWMS Code paragraph 4.20 requires the control and monitoring equipment to store data for at least 24 months.3
- Regulation E-1.1.4 requires an annual survey within three months before or after each anniversary date of the certificate.4
- Regulation E-1.1.2 requires a renewal survey at intervals not exceeding five years.4
Flag and class notes
Who may do the commissioning test is set by the flag and its recognised organisation. DNV requires a DNV-approved service supplier or an organisation accepted by the flag, sampling independent of the maker, local ambient water unless the flag agrees otherwise, and a written report; it notes that the flag may allow a case-by-case postponement, possibly with a condition, if the report or a laboratory is not available before departure.7 The Isle of Man registry asks for collection and analysis by an entity independent of the BWMS manufacturer or supplier and approved by the recognised organisation.5 Other class societies keep similar approved-supplier lists. Check with your recognised organisation before booking the test, and ask whether the flag adds anything.
Key numbers
| What | Value |
|---|---|
| Commissioning test mandatory from | 1 June 20221 |
| Minimum discharge sample volume | 1 m³, unless a smaller volume is validated2 |
| Size classes analysed | 50 micrometres and above; 10 to under 50 micrometres2 |
| D-2 limits for those classes | Fewer than 10 per m³; fewer than 10 per mL7 |
| Commissioning tests found non-compliant (Global TestNet, as reported) | About 20%8 |
| BWMS data storage | At least 24 months3 |
| Annual survey window | 3 months either side of the anniversary date4 |
| Renewal survey | Not more than 5 years4 |
| Tokyo MOU 2025 campaign detentions due to the CIC topic | 3010 |
What inspectors find
- “Is the BWMS operational?” was the most common deficiency in the Tokyo MOU’s 2025 campaign and the main ground for its 30 campaign detentions.10
- About 20% of commissioning tests reported by Global TestNet members were non-compliant, mostly for organisms of 50 micrometres and above; dirty tanks and piping are a common cause.8
- A Ballast Water Record Book that is not properly filled in drew the most negative answers (7.83%) in the Mediterranean MoU’s 2025 campaign, and was one of the three items behind about 89% of non-compliances in the Black Sea MoU’s. Failures, inoperability and bypasses belong under code F of the record book.13146
- Since 1 June 2022 the initial or additional survey for a BWMS installation must confirm that a commissioning test was done, so keep the test report on board: without it the ship has no evidence that the requirement of regulation E-1 was met.1
FAQ
Our BWMS was commissioned in 2021. Do we need a commissioning test now?
Not for that installation. The test is confirmed at the initial survey or the additional survey for installing a BWMS completed on or after 1 June 2022. A significant repair, replacement or change later can trigger an additional survey, and with it a commissioning test.
Can the BWMS manufacturer do the sampling?
The flag decides, but DNV and the Isle of Man registry both require sampling and analysis independent of the manufacturer or supplier. Most ships use an approved testing laboratory.
What if the harbour water is very clean and there are almost no organisms to treat?
The guidance says to use local ambient water however suitable it is for testing. A test in very clean water proves less, which is why characterising the uptake water is useful. If the water is unsuitable for practical reasons, agree an alternative with the flag.
Quiz6 questions
Sources
- 1
IMO Resolution MEPC.325(75), Amendments to the BWM Convention (commissioning testing of ballast water management systems and form of the IBWM Certificate), adopted 20 November 2020, in force 1 June 2022, operative paragraphs 3 to 5 and annex paragraphs 1 and 2 (regulation E-1.1.1 and E-1.1.5). https://wwwcdn.imo.org/localresources/en/KnowledgeCentre/IndexofIMOResolutions/MEPCDocuments/MEPC.325(75).pdf
- 2
IMO BWM.2/Circ.70/Rev.1, 2020 Guidance for the commissioning testing of ballast water management systems, 9 December 2020, annex paragraphs 1 to 5. The English text was not available to us online; paragraphs read in the German official translation published in VkBl. 2022 No. 8, p. 238. https://www.umwelt-online.de/recht/gefahr.gut/see/mepc/bwm2_70r1.htm
- 3
IMO Resolution MEPC.300(72), Code for Approval of Ballast Water Management Systems (BWMS Code), adopted 13 April 2018, annex paragraphs 4.17 to 4.20 and 8.2 to 8.3. https://wwwcdn.imo.org/localresources/en/KnowledgeCentre/IndexofIMOResolutions/MEPCDocuments/MEPC.300(72).pdf
- 4
International Convention for the Control and Management of Ships’ Ballast Water and Sediments, 2004 (BWM/CONF/36), annex regulation E-1, Surveys, paragraphs 1.2 to 1.5. https://mardep.gov.hk/filemanager/en/share/aboutus/pdf/scc/scc_p149a.pdf
- 5
Isle of Man Ship Registry, Technical Advisory Notice 001-22, Commissioning Tests for Ballast Water Management Systems (BWMS), 8 February 2022. https://iomshipregistry.com/media/kuvmhbry/001-22-commissioning-tests-for-ballast-water-management-systems-bwms.pdf
- 6
IMO Resolution MEPC.369(80), Amendments to the BWM Convention (Form of Ballast Water Record Book), adopted 7 July 2023, in force 1 February 2025, annex (codes A to H). https://wwwcdn.imo.org/localresources/en/KnowledgeCentre/IndexofIMOResolutions/MEPCDocuments/MEPC.369(80).pdf
- 7
DNV, Mandatory BWMS commissioning test required from 1 June 2022 (technical news). https://www.dnv.com/news/2022/mandatory-bwms-commissioning-test-required-from-1-june-2022-225958/
- 8
DHI Maritime Tech (E. Chua, G. I. Petersen, T. Madsen), Commissioning testing of Ballast Water Management Systems: best practice for sampling and analysis, technical note, 15 September 2022. https://ballastwater.dhigroup.com/wp-content/uploads/2022/11/Commissioning-testing-of-BWMS-best-practice-for-sampling-and-analysis.pdf
- 9
ABS, Regulatory News: IMO MEPC 84 Brief, 1 May 2026, section Amendments to Regulation E-1 (Surveys). https://ww2.eagle.org/content/dam/eagle/regulatory-news/2026/ABS-MEPC-84-Brief.pdf
- 10
Tokyo MOU Secretariat, Press release: Preliminary results of the CIC on Ballast Water Management 2025, 17 March 2026. https://www.tokyo-mou.org/press-releases/2026/03/17/preliminary-results-of-cic-on-ballast-water-management-2004
- 11
IMO Resolution MEPC.290(71), The experience-building phase associated with the BWM Convention, adopted 7 July 2017, operative paragraph 4. https://wwwcdn.imo.org/localresources/en/KnowledgeCentre/IndexofIMOResolutions/MEPCDocuments/MEPC.290(71).pdf
- 12
IMO BWM.2/Circ.42/Rev.2, 2020 Guidance on ballast water sampling and analysis for trial use in accordance with the BWM Convention and Guidelines (G2), 9 December 2020. Listed by IMO; contents index of the German official translation at https://www.umwelt-online.de/recht/gefahr.gut/see/mepc/bwm2_42r2_in.htm
- 13
Mediterranean MoU Secretariat, Press release PR3-2026 on the CIC on the Ballast Water Management Convention, 2 April 2026. https://www.medmou.org/Documents/PR3-2026.pdf
- 14
Black Sea MoU Secretariat, Press release: Preliminary results of the CIC on Ballast Water Management, 19 February 2026. https://bsmou.org/downloads/press-releases/BS%20MoU%20Press%20Release%20CIC%20on%20Ballast%20Water%20Management.pdf
Rules checked 20 October 2026. VSL Safety is not an approved training provider and doesn't issue certificates. These lessons don't replace STCW training, or the manufacturer's training and certification that service technicians need.